Porvorim flyover to fully reopen in 15-20 days

By News Desk··~1 min read

All entry and exit ramps on the Porvorim flyover will become operational within 15 to 20 days, Public Works Department officials said. Work continues on an arm allowing Porvorim residents to access the nearby Atal Setu, which remains blocked and has caused severe congestion on the approach roads.

The 5.1km, six-lane corridor reopens four months after access points closed following two fatal accidents within 48 hours of the flyover's September inauguration. PWD will install two additional AI cameras at the midpoint of the flyover to monitor speeds, alongside existing cameras at both ends. The system will automatically issue challans to speeding violators. Officials also plan to build slipways using additional funds from the ministry of road transport and highways.

Share